空壓機的停用在各個單位都常有發生。那(nà)麼在初次開機前空壓機停放時間超過三個(gè)月或空壓機停用時(shí)間(jiān)超過三個月,再次開機前需要采取有效措施,bi須先請專業空壓(yā)機人員對機器(qì)進行(háng)保養檢測,制定安全(quán)措施(shī),避免開機後發生不良狀況。
The shutdown of air compressors often occurs in various units. Then, before the first start-up, the air compressor parking time is more than three months or the air compressor parking time is more than three months. Before the second start-up, effective measures need to be taken. The Bi must first ask professional air compressor personnel to carry out maintenance and inspection of the machine, and formulate safety measures to avoid adverse conditions after the start-up.
1、先檢查電路狀态(tài),是否正常供(gòng)電,電壓是(shì)否(fǒu)穩定;測量電動(dòng)機(jī)絕(jué)緣電阻,數值大于1MΩ。
1. Check the state of the circuit first, whether the power supply is normal, whether the voltage is stable; Measure the insulation resistance of the motor, the value is greater than 1M.
2、檢查空壓(yā)機配件上是否含有積(jī)水,灰塵,及時清理。
2. Check whether there is water and dust on the spare parts of air compressor, and clean them up in time.
3、對進氣口,出氣口全面檢(jiǎn)測,防止發生堵塞現象
3. Overall inspection of intake and outlet to prevent blockage
4、在上述都已經完成的(de)情況可以接通電源(yuán),查看電腦控制器是否(fǒu)正常運行(háng)
4. If all the above have been completed, the power supply can be connected to check whether the computer controller is working properly.
5、更換三濾和潤(rùn)滑油。因為在長期不用的情況下,三濾(lǜ),油可能發生(shēng)老化(huà)現象,從而造成空壓機開機(jī)運行(háng)時間(jiān)不長即結膠積碳或堵塞,油路不(bú)暢使空壓機主機或其他零部件損壞。
5. Replace three filters and lubricants. Because in the case of long-term non-use, three filters may cause oil aging phenomenon, which causes the air compressor start-up time is not long, that is, cementing carbon deposit or blockage, oil circuit is not smooth, so that air compressor main engine or other parts are damaged.
6、專業人員試(shì)機,電路改造後人工控制加載卸載,先空載運行(háng)10分鐘以上,檢測各項指标和震動、噪音等正常,再進行(háng)加載,查看各部件運行正常即可。
6. Professional personnel test machine, after circuit modification, manual control loading and unloading, first no-load operation for more than 10 minutes, detection of various indicators and vibration, noise and other normal, then load, check the normal operation of the components.